User story #578: Edit Project with many lines. How will it look like on the board
User story #579: Assign Task to Area
User story #587: Sortable board cards
Task #584: Setup CI server
User story #583: Print Tasks
User story #578: Edit Project with many lines. How will it look like on the board
User story #579: Assign Task to Area
 
2023
2024
2025
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec
Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec
Jan
Feb
Mar
Apr
 4h
Underload: 4h

Total scheduled: 4h
Total: 8h
 1h
Underload: 1h

Total scheduled: 7h
Total: 8h
 1.5h
Underload: 1.5h

Total scheduled: 6.5h
Total: 8h
 F
Load: Full load

Total scheduled: 8h
Total: 8h
 Off
 Off
 -0.5h
Overload: 0.5h

Total scheduled: 8.5h
Total: 8h
 -4.5h
Overload: 4.5h

Total scheduled: 12.5h
Total: 8h
 1.5h
Underload: 1.5h

Total scheduled: 6.5h
Total: 8h
 
 
Release 3.0
 
Release 1.0
 
Release 2.0
 Edit Project with many lines. How will it look like on the board
Dates: Wed, 03 Apr - Thu, 18 Apr
Scheduled: 4 h/d for 6 days (10 days off)
Total: 24 hours for 6 days (10 days off)

Issue: User story #578: Edit Project with many lines. How will it look like on the board
Project: Redmine Agile plugin demo
Status: In Progress
Start date: 04/06/2024
Due date:
Assignee: Smith Paul
Author: Gibson Tyler
 Edit Project with many lines. How will it look like on the board
Dates: Wed, 24 Apr - Sun, 28 Apr
Scheduled: 4 h/d for 3 days (2 days off)
Total: 12 hours for 3 days (2 days off)

Issue: User story #578: Edit Project with many lines. How will it look like on the board
Project: Redmine Agile plugin demo
Status: In Progress
Start date: 04/06/2024
Due date:
Assignee: Smith Paul
Author: Gibson Tyler
 
 Assign Task to Area
Dates: Fri, 05 Apr - Sun, 07 Apr
Scheduled: 3 h/d for 1 day (2 days off)
Total: 3 hours for 1 day (2 days off)

Issue: User story #579: Assign Task to Area
Project: Redmine Agile plugin demo
Status: Resolved
Start date: 04/01/2024
Due date:
Assignee: Pong Steven
Author: Foster Andrew
 Sortable board cards
Dates: Sat, 06 Apr - Fri, 12 Apr
Scheduled: 2.5 h/d for 3 days (4 days off)
Total: 7.5 hours for 3 days (4 days off)

Issue: User story #587: Sortable board cards
Project: Redmine Agile plugin demo
Status: In Progress
Start date: 04/03/2024
Due date:
Assignee: Stone Elizabeth
Author: Stone Elizabeth
 Sortable board cards
Dates: Sat, 20 Apr - Thu, 25 Apr
Scheduled: 6 h/d for 4 days (2 days off)
Total: 24 hours for 4 days (2 days off)

Issue: User story #587: Sortable board cards
Project: Redmine Agile plugin demo
Status: In Progress
Start date: 04/03/2024
Due date:
Assignee: Stone Elizabeth
Author: Stone Elizabeth
 
 Setup CI server
Dates: Wed, 10 Apr - Sat, 13 Apr
Scheduled: 1.5 h/d for 1 day (3 days off)
Total: 1.5 hours for 1 day (3 days off)

Issue: Task #584: Setup CI server
Project: Redmine Agile plugin demo
Status: Resolved
Start date: 04/04/2024
Due date:
Assignee: Pong Steven
Author: Smith Paul
 
 Print Tasks
Dates: Tue, 16 Apr - Fri, 19 Apr
Scheduled: 5 h/d for 4 days
Total: 20 hours for 4 days

Issue: User story #583: Print Tasks
Project: Redmine Agile plugin demo
Status: New
Start date: 04/04/2024
Due date:
Assignee:
Author: Smith Paul
 
 F
Load: Full load

Total scheduled: 6h
Total: 6h
 1h
Underload: 1h

Total scheduled: 5h
Total: 6h
 Off
 -2h
Overload: 2h

Total scheduled: 8h
Total: 6h
 -3h
Overload: 3h

Total scheduled: 9h
Total: 6h
 
 
Release 3.0
 
Release 1.0
 
Release 2.0
 Edit Project with many lines. How will it look like on the board
Dates: Sat, 20 Apr - Fri, 26 Apr
Scheduled: 6 h/d for 5 days (2 days off)
Total: 30 hours for 5 days (2 days off)

Issue: User story #578: Edit Project with many lines. How will it look like on the board
Project: Redmine Agile plugin demo
Status: In Progress
Start date: 04/06/2024
Due date:
Assignee: Smith Paul
Author: Gibson Tyler
 Assign Task to Area
Dates: Sun, 07 Apr - Fri, 19 Apr
Scheduled: 5 h/d for 7 days (6 days off)
Total: 35 hours for 7 days (6 days off)

Issue: User story #579: Assign Task to Area
Project: Redmine Agile plugin demo
Status: Resolved
Start date: 04/01/2024
Due date:
Assignee: Pong Steven
Author: Foster Andrew
 
 1h
Underload: 1h

Total scheduled: 7h
Total: 8h
 1h
Underload: 1h

Total scheduled: 7h
Total: 8h
 
 
Release 3.0
 
Release 1.0
 
Release 2.0
 Setup CI server
Dates: Mon, 01 Apr - Wed, 10 Apr
Scheduled: 7 h/d for 8 days (2 days off)
Total: 56 hours for 8 days (2 days off)

Issue: Task #584: Setup CI server
Project: Redmine Agile plugin demo
Status: Resolved
Start date: 04/04/2024
Due date:
Assignee: Pong Steven
Author: Smith Paul
 